Task 3 Manage Impediments and Risk PMI-ACP Practice Questions (Page 5)
Part of the Domain 4 Delivery domain, which accounts for 28% of the PMI-ACP exam. PMI does not publish an official question count, but from its 180-minute exam (~70–120 total, ~20–34 in this domain), expect 3–5 from this objective — we provide 27 practice questions to prepare you well beyond it. (estimate)
27questions here
6free pages
5concepts
28%of the exam
Questions 21–25
- 21
During a sprint, an impediment that was thought to be resolved reappears. What is the most appropriate action for the team?
Select an answer first - 22
During iteration planning, the team identifies a significant risk that could delay delivery. According to agile principles, what is the most appropriate way to decide how to address this risk?
Select an answer first - 23
An agile team wants to proactively identify risks for an upcoming iteration. Which source of information is most likely to reveal risks that have occurred in similar past projects?
Select an answer first - 24
During a retrospective, the team identifies a recurring impediment that has slowed delivery in several sprints. What is the most effective way to prevent this impediment from continuing to affect future sprints?
Select an answer first - 25
A team has been tracking a risk that a key API might be deprecated. They implemented a mitigation to monitor the API vendor's announcements. After a few months, the team finds that the API is still active and no deprecation is planned. What should the team do?
Select an answer first