PMIAgile Certified Practitioner (PMI-ACP)
Domain 4Objective 3
Task 3 Manage Impediments and Risk PMI-ACP Practice Questions (Page 2)
Part of the Domain 4 Delivery domain, which accounts for 28% of the PMI-ACP exam. PMI does not publish an official question count, but from its 180-minute exam (~70–120 total, ~20–34 in this domain), expect 3–5 from this objective — we provide 27 practice questions to prepare you well beyond it. (estimate)
27questions here
6free pages
5concepts
28%of the exam
Questions 6–10
- 6
During a sprint, a critical impediment arises: a vendor has not delivered a promised component, blocking the team's work. The Scrum Master has called an emergency meeting. What is the best way to determine the course of action?
Select an answer first - 7
A team has identified two risks: (1) a critical bug in a third-party library may affect the product, and (2) a non-critical feature may be delayed. The team has limited capacity. Which risk should be addressed first?
Select an answer first - 8
An agile team is starting a new project and wants to identify potential risks and impediments proactively. Which technique is specifically designed to leverage the collective knowledge of the team to surface a wide range of possible risks?
Select an answer first - 9
An agile team has identified two impediments: one that will delay the current sprint by two days, and another that is a minor inconvenience with no impact on the sprint goal. According to agile prioritization principles, which impediment should the team address first?
Select an answer first - 10
When prioritizing risk mitigation activities, which factor should an agile team consider as the most important?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.