Part of the Strategic Alignment domain, which accounts for 25% of the PFMP exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~24–40 in this domain), expect 3–5 from this objective — we provide 35 practice questions to prepare you well beyond it. (estimate)
35questions here
7free pages
10concepts
25%of the exam
Questions 16–20
- 16
What is the role of governance in maintaining strategic alignment?
Select an answer first - 17
A government agency is developing its annual portfolio. The strategic plan includes improving digital services for citizens, reducing processing times, and increasing transparency. The agency's IT department has proposed several projects, including a new online portal, a data analytics platform, and a legacy system modernization. The agency's budget office has also proposed a project to upgrade office furniture. How should the portfolio manager integrate the strategic plan with the portfolio?
Select an answer first - 18
A portfolio manager at a bank is mapping portfolio components to strategic objectives. The strategic objectives are: (1) increase digital adoption, (2) improve risk management, and (3) reduce operational costs. The portfolio includes the following components: a mobile banking app upgrade, a new fraud detection system, a branch network optimization project, and a customer data platform implementation. Which component should be mapped to the objective of improving risk management?
Select an answer first - 19
A healthcare organization's portfolio includes a mix of projects and programs. The strategic objectives are to improve patient outcomes, reduce operational costs, and expand telemedicine services. The portfolio manager is reviewing the portfolio performance dashboard. Which set of metrics would best indicate the portfolio's alignment with the strategy?
Select an answer first - 20
A large retail chain has a portfolio that includes a project to implement a new point-of-sale system, a program to revamp the supply chain, and a project to launch a customer loyalty program. The organization's strategy is to enhance customer experience and improve operational efficiency. The governance board is reviewing the portfolio and notices that the loyalty program project is consuming a disproportionate amount of resources and is behind schedule. The board is considering whether to continue, modify, or terminate the project. What should the governance board do to maintain strategic alignment?
Select an answer first