Part of the Portfolio Risk Management domain, which accounts for 15% of the PFMP exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~14–24 in this domain), expect 2–4 from this objective — we provide 28 practice questions to prepare you well beyond it. (estimate)

28questions here
6free pages
5concepts
15%of the exam

Questions 26–28

  1. 26application · medium

    A portfolio manager is updating the risk register after implementing a risk response. What should be included in the update?

    Select an answer first
  2. 27foundation · easy

    What should be done if monitoring reveals that a risk response is not effectively reducing risk to the desired level?

    Select an answer first
  3. 28application · medium

    A portfolio risk response involves shifting a critical resource from a project that is on schedule to a project that is at risk of missing a regulatory deadline. The project manager of the on-schedule project objects. What should the portfolio manager do?

    Select an answer first
Finished these 3 questions?

Review the revealed explanations, or continue through the curriculum.

No more pagesBack to PFMP

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PFMP” is a trademark of its owner, used for identification only.