Part of the Portfolio Risk Management domain, which accounts for 15% of the PFMP exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~14–24 in this domain), expect 2–4 from this objective — we provide 28 practice questions to prepare you well beyond it. (estimate)
28questions here
6free pages
5concepts
15%of the exam
Questions 6–10
- 6
A portfolio risk response has been implemented, but a key stakeholder is unaware of the progress and is concerned about the risk. What should the portfolio manager do?
Select an answer first - 7
A portfolio manager is planning responses for a high-impact risk that could delay a regulatory approval critical to three projects. The portfolio has limited funds and cannot afford to implement all possible responses. The governance board requires a response that is cost-effective and does not delay the projects. Which approach is most appropriate?
Select an answer first - 8
When implementing portfolio risk responses, what must be ensured to maintain alignment with portfolio governance?
Select an answer first - 9
A portfolio risk response has been implemented, and the risk level is decreasing. The portfolio manager needs to communicate this to the governance board. What is the most appropriate way to report?
Select an answer first - 10
A portfolio risk response is being implemented, but the response owner is not following the plan, and the risk level is not decreasing as expected. The portfolio manager has limited authority to enforce compliance. What should the portfolio manager do?
Select an answer first