Part of the Portfolio Risk Management domain, which accounts for 15% of the PFMP exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~14–24 in this domain), expect 2–4 from this objective — we provide 26 practice questions to prepare you well beyond it. (estimate)
26questions here
6free pages
6concepts
15%of the exam
Questions 26–26
- 26
A portfolio manager has developed risk responses for a portfolio of projects, including a mitigation plan for a key resource shortage and a transfer strategy for regulatory fines. The manager now needs to implement these responses. What is the most effective way to ensure the responses are integrated into portfolio plans and processes?
Select an answer first
Finished these 1 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PFMP
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PFMP” is a trademark of its owner, used for identification only.