Part of the Portfolio Risk Management domain, which accounts for 15% of the PFMP exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~14–24 in this domain), expect 2–4 from this objective — we provide 26 practice questions to prepare you well beyond it. (estimate)
26questions here
6free pages
6concepts
15%of the exam
Questions 21–25
- 21
A portfolio manager has identified a list of risks for a portfolio of IT projects. The risks include a potential data breach, a delay in a critical vendor delivery, and a change in regulatory compliance requirements. The manager needs to analyze these risks to determine their likelihood, impact, and interdependencies. Which approach best supports this analysis?
Select an answer first - 22
A portfolio manager has been monitoring risks for a portfolio of projects. During a review, the manager finds that a risk response that was implemented is not working as expected. The risk is still high, and the response has consumed significant resources. What is the most appropriate action?
Select an answer first - 23
During portfolio risk identification, which activity is most directly associated with this process?
Select an answer first - 24
Which activity is part of analyzing portfolio risks?
Select an answer first - 25
What is the main purpose of prioritizing portfolio risks?
Select an answer first