  1. 21foundation · easy

    A project has a fixed completion date. The project manager discovers that a non-critical task can be delayed without affecting the overall project timeline. What is this scheduling flexibility called?

    Select an answer first
  2. 22expert · hard

    A project has a critical path of 20 weeks. The sponsor requires completion in 18 weeks. The project manager has two options: crash an activity by adding $10,000 to reduce the schedule by 2 weeks, or fast track two sequential activities to overlap by 2 weeks, which introduces a 20% risk of rework. The budget has a $15,000 contingency reserve. What is the most appropriate decision?

    Select an answer first
  3. 23expert · hard

    A project has identified a risk that a key supplier may go out of business. The risk register includes a mitigation strategy to identify an alternative supplier. However, the alternative supplier charges 20% more. The project budget has no contingency reserve. What should the project manager do?

    Select an answer first
  4. 24application · medium

    A project has a budget of $100,000. The cost estimate is $95,000, but a risk assessment identified a potential $10,000 overrun due to material price volatility. The sponsor wants to avoid a budget increase. What should the project manager do?

    Select an answer first
  5. 25application · medium

    A software upgrade project has three critical path activities: coding (10 days), testing (5 days), and deployment (2 days). Testing cannot start until coding is complete, and deployment cannot start until testing is complete. The sponsor needs the project finished 3 days earlier. Which action would most likely achieve the target without adding risk?

    Select an answer first