Questions 6–10
- 6
A project has a stakeholder with high interest but low influence who frequently asks for detailed technical reports. The project manager has limited time. What is the best approach?
Select an answer first - 7
What is the most effective way to prevent scope creep during project execution?
Select an answer first - 8
A project has two stakeholder groups: Group A has high power and high interest, Group B has low power and low interest. The project manager has limited time. A new regulation requires additional reporting that will affect both groups. How should the project manager adjust the stakeholder engagement plan?
Select an answer first - 9
During project execution, a cost estimate for a key deliverable increases by 15% due to new regulatory requirements. The project has a fixed budget with no contingency reserve. What is the most appropriate first action for the project manager?
Select an answer first - 10
A project manager is preparing the project budget. The team has provided cost estimates for each work package, but the organization has a strict financial constraint that requires a 10% reduction in total costs. What is the most appropriate action?
Select an answer first