Task 2 Manage Project Change Control in Alignment with Sustainability Objectives CSPP Practice Questions (Page 1)
Part of the Project Management Considerations domain, which accounts for N/A / 23% of the CSPP exam.
24questions here
5free pages
4concepts
N/A / 23%of the exam
Questions 1–5
- 1
A project manager is leading a sustainability initiative to reduce packaging waste. The change management lead and the project manager have conflicting priorities: the project manager wants to meet the project schedule, while the change management lead wants to slow down to ensure employee adoption. The project is at risk of failing if employees do not adopt the new packaging processes. What is the BEST way to reconcile these priorities?
Select an answer first - 2
A project manager is applying the Organizational Change Management (OCM) process to a project that will replace a legacy reporting system with a more energy-efficient cloud solution. Which activity is part of the 'executing' phase of OCM?
Select an answer first - 3
A manufacturing company is transitioning to a circular economy model, requiring a significant change in production processes. The project manager wants to use a change model that emphasizes unfreezing current practices, moving to new behaviors, and refreezing to sustain the change. Which change model should the project manager apply?
Select an answer first - 4
A change management team is helping employees move from their current way of working to a new sustainable process. According to Lewin's change model, which process describes the stage where employees let go of old behaviors and become open to the new way?
Select an answer first - 5
A project manager is leading a change to adopt renewable energy sources. The change is facing resistance from employees who are concerned about job security. The project manager wants to use a change model that focuses on creating a sense of urgency and building a guiding coalition to overcome resistance. Which change model should the project manager apply?
Select an answer first