Questions 11–15
- 11
A project has a stakeholder who is highly influential but has low interest. The stakeholder's approval is required for a major deliverable. The project manager needs to ensure the stakeholder reviews and approves the deliverable on time. What is the best approach?
Select an answer first - 12
A project manager is creating a risk register for a water conservation project. Which of the following is the most appropriate entry?
Select an answer first - 13
A project schedule has a critical path of 12 weeks. A key team member is only available for 8 of those weeks, which will delay the project. What is the most appropriate scheduling adjustment?
Select an answer first - 14
Which of the following is a required element in an issues log?
Select an answer first - 15
A construction project has a fixed budget of $500,000 and a deadline in 6 months. The initial cost estimate was $480,000, but a required environmental review adds $30,000. The schedule has no float. What should the project manager do first?
Select an answer first