Task 1 Demonstrate an Understanding of the Various Project Life Cycles and Processes. CAPM Practice Questions (Page 7)
Part of the Project Management Fundamentals and Core Concepts domain, which accounts for 36% of the CAPM exam. PMI does not publish an official question count, but from its 180-minute exam (~70–120 total, ~25–43 in this domain), expect 5–9 from this objective — we provide 31 practice questions to prepare you well beyond it. (estimate)
31questions here
7free pages
7concepts
36%of the exam
Questions 31–31
- 31
A project to launch a new product has a fixed deadline. The team discovers that a key component is unavailable from the primary supplier, but an alternative supplier can deliver it at a higher cost. The project manager must decide whether to use the alternative supplier. What is the fixed deadline in this scenario?
Select an answer first
Finished these 1 questions?
Review the revealed explanations, or continue through the curriculum.