Part of the Understand how to apply the PRINCE2 principles in context domain, which accounts for 10% of the PRINCE2-PRACTITIONER-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 150-minute exam (~60–100 total, ~6–10 in this domain), expect 6–10 from this objective — we provide 28 practice questions to prepare you well beyond it. (estimate)

28questions here
6free pages
7concepts
10%of the exam

Questions 16–20

  1. 16application · medium

    A large manufacturing company is running a high-risk project to automate its production line. The project manager has decided to use a full PRINCE2 approach with all roles and processes. However, the project board wants to reduce the number of management products to save time. What should the project manager do?

    Select an answer first
  2. 17application · medium

    A government agency is running a project to implement a new tax filing system. Midway through, a new regulation makes one of the system's core features obsolete. The project manager has updated the business case, but the project board is uncertain whether to continue. What should the project manager do to support the board's decision?

    Select an answer first
  3. 18application · medium

    A bank is running a project to develop a new mobile banking app. The project manager has defined the products, but the business stakeholders have not agreed on the quality criteria for the app's security features. The project manager wants to apply the focus on products principle. What should the project manager do?

    Select an answer first
  4. 19foundation · easy

    What is the purpose of the 'manage by stages' principle in PRINCE2?

    Select an answer first
  5. 20expert · hard

    A construction company is running a 2-year project to build a new office complex. The project board wants to review progress at the end of each major phase, but the project manager has planned the entire project in detail upfront. The project board is concerned about the lack of control. What should the project manager do?

    Select an answer first