5.2 Explain the Objectives of the PRINCE2 Processes PRINCE2-FOUNDATION-VERSION-7 Practice Questions (Page 6)
Part of the Understand the PRINCE2 processes and how they are carried out throughout the project domain, which accounts for 15% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~4–6 in this domain), expect 1–2 from this objective — we provide 30 practice questions to prepare you well beyond it. (estimate)
30questions here
6free pages
7concepts
15%of the exam
Questions 26–30
- 26
At the end of a stage, the project manager prepares a stage boundary report and an updated business case. What is the purpose of these documents?
Select an answer first - 27
A project manager is asked to start a project, but the project mandate is unclear and there is no executive sponsor yet. According to PRINCE2, what should happen during Starting up a Project?
Select an answer first - 28
A project board is reviewing a stage boundary report and notices that the project's costs are significantly over budget, but the stage is almost complete. The project board must decide whether to authorize the next stage. What should the project board consider?
Select an answer first - 29
What is the main purpose of the Controlling a Stage process?
Select an answer first - 30
Which of the following is an objective of the Controlling a Stage process?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.