Part of the The integration of PRINCE2 Agile in the wider context domain, which accounts for 5.0% of the PRINCE2-AGILE-FOUNDATION-V2 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~1–1 in this domain), expect 1–1 from this objective — we provide 29 practice questions to prepare you well beyond it. (estimate)
29questions here
6free pages
5concepts
5.0%of the exam
Questions 6–10
- 6
A PRINCE2 Agile project has delivered a new customer relationship management (CRM) system. The project is closing, and the operations team will take over support. The operations team is concerned about the system's performance and wants to ensure they can monitor it effectively. What should the project team provide to operations to support a smooth handover?
Select an answer first - 7
In agile product management, what is the primary focus when planning and delivering a product over time?
Select an answer first - 8
A PRINCE2 Agile project has delivered a new data analytics platform. The project is closing, and the operations team will take over. The operations team is unfamiliar with the platform and is concerned about their ability to support it. The project team has limited time for handover activities. What is the most effective way to ensure a smooth handover?
Select an answer first - 9
A company has adopted PRINCE2 Agile for its projects and is now looking to extend agile practices into operations. The goal is to release updates to its web application more frequently and to improve collaboration between development and operations teams. Which practice is most aligned with this goal?
Select an answer first - 10
A PRINCE2 Agile project has delivered a new customer-facing web application. The project is closing, and the operations team will take over. The operations team is concerned about the application's performance and wants to ensure they can respond to performance issues quickly. The project team has limited time for handover. What is the most effective way to ensure the operations team can respond to performance issues?
Select an answer first