Part of the Understand how to apply and tailor relevant aspects of the MSP processes in context domain, which makes up ~52% of our current practice bank. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~13–21 in this domain), expect 2–3 from this objective — we provide 33 practice questions to prepare you well beyond it. (estimate)
33questions here
7free pages
7concepts
Questions 16–20
- 16
A programme is closing, and the programme manager is ensuring that all project outputs are integrated into business operations. Which activity is being performed?
Select an answer first - 17
What is the primary purpose of the Close the Programme process in MSP?
Select an answer first - 18
A programme is closing after achieving its objectives. The programme board is meeting to make the final closure decision. What is the programme board's primary responsibility during this meeting?
Select an answer first - 19
During Close the Programme, the programme manager is coordinating the handover of project outputs to business as usual. Who is responsible for ensuring that the handover is completed effectively?
Select an answer first - 20
A programme is closing, but the programme board is concerned that the closure process is too bureaucratic for the programme's size. The programme is small and has a simple governance structure. What is the most appropriate way to tailor the Close the Programme process?
Select an answer first