Plan-Do-Check-Act Cycle CT-ATLAS Practice Questions (Page 6)
Part of the Continuous Improvement of Quality and Testing domain, which makes up ~17% of our current practice bank. ISTQB does not publish an official question count, but from its 120-minute exam (~50–80 total, ~9–14 in this domain), expect 2–3 from this objective — we provide 26 practice questions to prepare you well beyond it. (estimate)
26questions here
6free pages
6concepts
Questions 26–26
- 26
A testing team ran a PDCA cycle to improve their defect detection rate. The Check phase shows that the new testing technique increased defect detection by 20%, but also increased test execution time by 40%. The team has a constraint: they cannot increase test execution time beyond 25%. What should they do in the Check phase?
Select an answer first
Finished these 1 questions?
Review the revealed explanations, or continue through the curriculum.