Plan-Do-Check-Act Cycle CT-ATLAS Practice Questions (Page 1)

Part of the Continuous Improvement of Quality and Testing domain, which makes up ~17% of our current practice bank. ISTQB does not publish an official question count, but from its 120-minute exam (~50–80 total, ~9–14 in this domain), expect 2–3 from this objective — we provide 26 practice questions to prepare you well beyond it. (estimate)

26questions here
6free pages
6concepts

Questions 1–5

  1. 1application · medium

    After a pilot to improve test execution time, the team collects data showing a 10% reduction, but the target was 20%. What is the most appropriate action in the Check phase?

    Select an answer first
  2. 2foundation · easy

    What is the main purpose of the Act phase in the PDCA cycle?

    Select an answer first
  3. 3application · medium

    A testing team plans to pilot a new exploratory testing technique on one feature to see if it increases defect discovery. They have defined metrics and a baseline. What is the most appropriate action for the Do phase?

    Select an answer first
  4. 4application · medium

    A testing team completes a PDCA cycle to improve their test case review process. The Check phase shows that the new review checklist reduced defects escaping to production by 25%, exceeding the target. What should the team do in the Act phase?

    Select an answer first
  5. 5foundation · easy

    In the Plan phase of PDCA, what is the primary focus?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.