Project Initiation PK0-005 Practice Questions (Page 3)
Part of the Project life cycle phases domain, which accounts for 30% of the PK0-005 exam. CompTIA does not publish an official question count, but from its 90-minute exam (~35–60 total, ~11–18 in this domain), expect 2–4 from this objective — we provide 13 practice questions to prepare you well beyond it. (estimate)
13questions here
3free pages
4concepts
30%of the exam
Questions 11–13
- 11
Which document defines the roles and responsibilities of team members for each project task?
Select an answer first - 12
A project manager is initiating a project to upgrade the company's customer relationship management (CRM) system. The project sponsor has approved the business case, and the project manager is now identifying stakeholders. During a preliminary analysis, the project manager discovers that the sales director has high influence over the project's funding and is strongly opposed to the upgrade because it will change the sales team's daily workflow. The project manager also notes that the IT support team has low influence but will be heavily impacted by the new system's maintenance requirements. Which of the following is the MOST appropriate initial action for the project manager?
Select an answer first - 13
A stakeholder has high power over the project but low interest in its outcomes. According to a power/interest grid, how should the project manager best engage this stakeholder?
Select an answer first
Finished these 3 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PK0-005
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by CompTIA. “PK0-005” is a trademark of its owner, used for identification only.