Procurement and Vendor Selection PK0-005 Practice Questions (Page 7)
Part of the Project management concepts domain, which accounts for 33% of the PK0-005 exam. CompTIA does not publish an official question count, but from its 90-minute exam (~35–60 total, ~12–20 in this domain), expect 1–2 from this objective — we provide 34 practice questions to prepare you well beyond it. (estimate)
34questions here
7free pages
9concepts
33%of the exam
Questions 31–34
- 31
What is the primary purpose of contract negotiation in procurement?
Select an answer first - 32
A project manager is in the final stage of vendor selection. Two vendors have scored very closely in the evaluation. Vendor X has a slightly higher technical score but a lower past performance score. Vendor Y has a slightly lower technical score but a higher past performance score. The project is critical to the organization's strategic goals. Which vendor should be selected?
Select an answer first - 33
Which of the following is a common risk associated with relying on a single vendor for a critical project component?
Select an answer first - 34
A project manager is evaluating a vendor that will provide a critical component for a new product launch. The vendor is a small company that has been in business for only two years. The project manager has identified several risks. Which of the following are appropriate risk mitigation strategies? (Select all that apply.)
Select an answer first
Finished these 4 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PK0-005
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by CompTIA. “PK0-005” is a trademark of its owner, used for identification only.