Part of the Project life cycle phases domain, which accounts for 30% of the PK0-005 exam. CompTIA does not publish an official question count, but from its 90-minute exam (~35–60 total, ~11–18 in this domain), expect 2–4 from this objective — we provide 30 practice questions to prepare you well beyond it. (estimate)
30questions here
6free pages
7concepts
30%of the exam
Questions 16–20
- 16
What is the purpose of vendor prequalification during the discovery phase?
Select an answer first - 17
In a cost-benefit analysis, what does a positive net benefit indicate?
Select an answer first - 18
What is the primary purpose of a business case in the discovery phase of a project?
Select an answer first - 19
A project manager is evaluating a project that requires an initial investment of $80,000. The project is expected to generate $20,000 in annual savings for 6 years. What is the simple payback period for this project?
Select an answer first - 20
A project manager is prequalifying vendors for a complex IT project. The project requires a vendor with a specific security certification (ISO 27001) and experience with a niche technology. The project manager has received responses from five vendors. Three vendors meet the mandatory criteria, and two do not. What is the most appropriate next step?
Select an answer first