Part of the Project life cycle phases domain, which accounts for 30% of the PK0-005 exam. CompTIA does not publish an official question count, but from its 90-minute exam (~35–60 total, ~11–18 in this domain), expect 2–4 from this objective — we provide 30 practice questions to prepare you well beyond it. (estimate)
30questions here
6free pages
7concepts
30%of the exam
Questions 6–10
- 6
In project financial analysis, what does cost-benefit analysis compare?
Select an answer first - 7
What does return on investment (ROI) measure in a project?
Select an answer first - 8
A project manager is selecting a vendor from a prequalified list for a data migration project. The project has a strict deadline, and the vendor must be able to start immediately. Which vendor selection criterion is most critical in this scenario?
Select an answer first - 9
In a business case, which component describes the potential negative outcomes that could affect the project's success?
Select an answer first - 10
A company is considering a project with an initial cost of $40,000. The project is expected to generate $15,000 in annual benefits for 4 years. What is the net benefit of this project?
Select an answer first