Examers.io
ExamsOrganizationsHow it worksPricingHelp & FAQ
CompTIA logo

CompTIAProject+

Domain 2Objective 1

Discovery Phase Artifacts PK0-005 Practice Questions (Page 2)

Part of the Project life cycle phases domain, which accounts for 30% of the PK0-005 exam. CompTIA does not publish an official question count, but from its 90-minute exam (~35–60 total, ~11–18 in this domain), expect 2–4 from this objective — we provide 30 practice questions to prepare you well beyond it. (estimate)

30questions here
6free pages
7concepts
30%of the exam

Questions 6–10

  1. 6foundation · easy

    In project financial analysis, what does cost-benefit analysis compare?

    Select an answer first
  2. 7foundation · easy

    What does return on investment (ROI) measure in a project?

    Select an answer first
  3. 8application · medium

    A project manager is selecting a vendor from a prequalified list for a data migration project. The project has a strict deadline, and the vendor must be able to start immediately. Which vendor selection criterion is most critical in this scenario?

    Select an answer first
  4. 9foundation · easy

    In a business case, which component describes the potential negative outcomes that could affect the project's success?

    Select an answer first
  5. 10application · medium

    A company is considering a project with an initial cost of $40,000. The project is expected to generate $15,000 in annual benefits for 4 years. What is the net benefit of this project?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by CompTIA. “PK0-005” is a trademark of its owner, used for identification only.