Managing PMO Resources PMI-PMOCP Practice Questions (Page 4)
Part of the PMO Operation and Performance domain, which accounts for 15% of the PMI-PMOCP exam. PMI does not publish an official question count, but from its 165-minute exam (~65–110 total, ~10–17 in this domain), expect 3–6 from this objective — we provide 25 practice questions to prepare you well beyond it. (estimate)
25questions here
5free pages
4concepts
15%of the exam
Questions 16–20
- 16
A PMO uses external contractors for specialized skills. The PMO manager wants to ensure that contractors are integrated into the PMO's ways of working. Which practice is most effective?
Select an answer first - 17
A PMO has a capacity planning process that uses a skills matrix to assign resources. The PMO is facing a conflict: a senior project manager with excellent stakeholder management skills is the only person available for a high-priority project, but the project requires deep technical expertise that the senior PM lacks. A junior PM with the technical skills is available. What is the best course of action?
Select an answer first - 18
A PMO is developing a resource management plan. The PMO has a mix of senior and junior project managers. Senior PMs are often assigned to complex projects, while junior PMs handle simpler ones. However, junior PMs are not gaining the experience needed to advance. The PMO manager wants to align resources with service demands while developing staff. What should the plan include?
Select an answer first - 19
A PMO is implementing a skills matrix. The matrix shows that the PMO has a surplus of project managers with communication skills but a shortage of those with data analysis skills. The PMO manager wants to optimize resource utilization. What should the manager do?
Select an answer first - 20
A PMO supports three business units with varying project demand: one unit has a predictable pipeline, another has seasonal peaks, and the third frequently requests urgent, small initiatives. The PMO manager must develop a resource management plan that aligns PMO staff with these service demands while avoiding overstaffing. Which approach best addresses this requirement?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.