Part of the Traceability and Monitoring domain, which accounts for 15% of the PMI-PBA exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~14–24 in this domain), expect 3–5 from this objective — we provide 29 practice questions to prepare you well beyond it. (estimate)
29questions here
6free pages
5concepts
15%of the exam
Questions 16–20
- 16
A BA is managing a change request that affects multiple requirements. The impact analysis shows that the change will delay the project by two weeks and increase costs by 5%. The sponsor is willing to accept the delay and cost increase, but the BA is concerned about the impact on a related requirement that is critical to regulatory compliance. What should the BA do?
Select an answer first - 17
A BA is tracking requirements on a project where the development team reports that a requirement is 'code complete' but has not yet been tested. The BA needs to update the requirement status. What status should the BA assign?
Select an answer first - 18
A BA is preparing a monthly status report for a large program. The report will be reviewed by the program sponsor, who is primarily interested in whether the project is on track to deliver the expected business value. Which type of report would be most useful to the sponsor?
Select an answer first - 19
A BA is working on a project where the requirements are not well-defined and the scope is expected to evolve. The BA needs to establish a traceability approach that supports change control and monitoring. What should the BA do?
Select an answer first - 20
Which of the following is an example of a traceability and monitoring report?
Select an answer first