Part of the Traceability and Monitoring domain, which accounts for 15% of the PMI-PBA exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~14–24 in this domain), expect 3–5 from this objective — we provide 33 practice questions to prepare you well beyond it. (estimate)
33questions here
7free pages
10concepts
15%of the exam
Questions 11–15
- 11
A business analyst is defining traceability governance for a project where requirements change frequently during the development phase. The team is struggling because the matrix is often out of date, and the monthly status report to the steering committee is questioned for accuracy. The BA needs a governance approach that balances the need for current data with the cost of constant updates. What should the BA recommend?
Select an answer first - 12
What does versioning in traceability governance ensure?
Select an answer first - 13
What should traceability reporting specify?
Select an answer first - 14
A business analyst is defining the traceability approach for a project that must integrate with an existing vendor system. The vendor will not share their internal design documents, but they will provide a list of delivered interfaces. The project must demonstrate that every business requirement is addressed by either a custom component or a vendor interface. What should the BA include in the traceability approach?
Select an answer first - 15
What does a traceability metric like 'coverage' measure?
Select an answer first