Part of the Identify Business Needs and Solutions domain, which accounts for 26% of the PMI-CPMAI exam. PMI does not publish an official question count, but from its 160-minute exam (~65–105 total, ~17–27 in this domain), expect 2–3 from this objective — we provide 27 practice questions to prepare you well beyond it. (estimate)
27questions here
6free pages
5concepts
26%of the exam
Questions 11–15
- 11
An e-commerce company is implementing an AI system to personalize product recommendations. The project sponsor wants to increase average order value by 15%. The data science team has built a model that recommends products based on browsing history. The marketing team is concerned that the model may recommend out-of-stock items, leading to customer frustration. The project manager is defining success criteria. Which success metric is most appropriate?
Select an answer first - 12
When the available resources are insufficient to deliver the full AI project scope, what is an appropriate action?
Select an answer first - 13
A multinational bank is developing an AI system for credit scoring. The project team has access to customer data from multiple countries. The legal team has stated that the model must comply with the EU's General Data Protection Regulation (GDPR), which restricts the use of certain personal data. The project manager is documenting assumptions and constraints. Which item should be documented as a CONSTRAINT?
Select an answer first - 14
An insurance company is developing an AI system to automate claims processing. The project sponsor wants the system to reduce the average claims processing time from 10 days to 3 days. The data science team notes that the model's precision must be high to avoid incorrectly denying valid claims. The project manager is defining success criteria. Which combination of metrics best captures the project's success?
Select an answer first - 15
A logistics company is implementing an AI model to predict delivery delays. The operations director wants the model to flag at-risk shipments so dispatchers can re-route them. The project manager is defining success criteria. Which success metric is most appropriate for evaluating the model's business value?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-CPMAI” is a trademark of its owner, used for identification only.