Part of the Domain 4 Delivery domain, which accounts for 28% of the PMI-ACP exam. PMI does not publish an official question count, but from its 180-minute exam (~70–120 total, ~20–34 in this domain), expect 3–5 from this objective — we provide 33 practice questions to prepare you well beyond it. (estimate)
33questions here
7free pages
8concepts
28%of the exam
Questions 26–30
- 26
What is a common strategy to shield a team from interruptions?
Select an answer first - 27
After implementing a change to improve flow, what should the team do to evaluate its impact?
Select an answer first - 28
Why is it important to have a designated point of contact for a team?
Select an answer first - 29
A team has a WIP limit of 4 items and a throughput of 2 items per day. What is the average cycle time?
Select an answer first - 30
A team currently has an average of 10 work items in progress and completes 5 items per week. After implementing WIP limits, the team reduces the average WIP to 6 items while maintaining the same throughput of 5 items per week. What is the new average cycle time?
Select an answer first