Part of the Domain 4 Delivery domain, which accounts for 28% of the PMI-ACP exam. PMI does not publish an official question count, but from its 180-minute exam (~70–120 total, ~20–34 in this domain), expect 3–5 from this objective — we provide 25 practice questions to prepare you well beyond it. (estimate)
25questions here
5free pages
4concepts
28%of the exam
Questions 16–20
- 16
A project sponsor wants a high-level view of project health and progress without detailed technical data. Which metric is most appropriate to report?
Select an answer first - 17
A team's cumulative flow diagram shows the 'In Progress' band widening over the last four sprints while the 'Done' band stays flat. The team is not changing scope. What is the most likely interpretation and the best next action?
Select an answer first - 18
A team notices that their cycle time has been increasing steadily over the last four sprints. What is the most appropriate first step in analyzing this metric?
Select an answer first - 19
A team's defect count has been increasing, and the product owner is concerned about quality. The team's velocity is stable. The team is considering adding a quality metric to the dashboard. Which metric would best help the team identify the root cause of the defect increase?
Select an answer first - 20
A team is using a digital dashboard that shows velocity, cycle time, and defect count. The team notices that stakeholders are not looking at the dashboard. The team wants to increase stakeholder engagement with the metrics. What should the team do?
Select an answer first