Part of the Portfolio Risk Management domain, which accounts for 15% of the PFMP exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~14–24 in this domain), expect 2–4 from this objective — we provide 32 practice questions to prepare you well beyond it. (estimate)

32questions here
7free pages
8concepts
15%of the exam

Questions 31–32

  1. 31application · medium

    A portfolio has a risk that could cause a significant delay to a strategic initiative. The risk has a 30% probability of occurring. If it occurs, it would cost $2 million. The portfolio has a risk response budget of $500,000. Which option is the most appropriate response?

    Select an answer first
  2. 32foundation · easy

    Which source of information is most appropriate for identifying portfolio-level risks?

    Select an answer first
Finished these 2 questions?

Review the revealed explanations, or continue through the curriculum.

No more pagesBack to PFMP

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PFMP” is a trademark of its owner, used for identification only.