Part of the Communications Management domain, which accounts for 15% of the PFMP exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~14–24 in this domain), expect 2–4 from this objective — we provide 29 practice questions to prepare you well beyond it. (estimate)

29questions here
6free pages
5concepts
15%of the exam

Questions 16–20

  1. 16expert · hard

    A portfolio manager is leading a portfolio that includes a highly confidential project. The project's stakeholders are limited to a small group, and the information is sensitive. The portfolio manager must ensure that communication about this project is restricted and does not inadvertently reach other stakeholders. What is the best approach?

    Select an answer first
  2. 17application · medium

    A portfolio manager is leading a large transformation portfolio with stakeholders across multiple time zones. The executive sponsor wants a monthly dashboard, while the program managers need weekly updates on dependencies and risks. The portfolio manager must ensure all stakeholders receive the information they need without overwhelming them. What should the portfolio manager do first?

    Select an answer first
  3. 18application · medium

    A portfolio manager is developing a communications management plan for a new portfolio. The plan must document how information will be shared with stakeholders, including the frequency and format. What is the most important element to include in the plan?

    Select an answer first
  4. 19expert · hard

    A portfolio manager is managing a portfolio with a mix of stable, ongoing programs and rapidly changing projects. The executive team wants to be informed of major changes immediately, but also wants to avoid information overload. What is the best way to establish a communication cadence that balances these needs?

    Select an answer first
  5. 20expert · hard

    A portfolio manager is setting up communications for a portfolio that includes a project with a very tight deadline. The project team needs daily updates on progress, while the executive sponsor only wants to be informed of major milestones. What is the best way to manage this communication cadence?

    Select an answer first