Questions 31–32
- 31
After a major portfolio review, the PRB notices that decisions are taking too long because the board is reviewing every component in detail, even those with low risk and low strategic impact. The portfolio manager wants to improve the governance process. What should the portfolio manager propose?
Select an answer first - 32
A portfolio governance framework defines that all components must have a business case approved by the PRB before funding. A component that is already underway has encountered a critical issue: the sponsor wants to add a new scope that would increase the component's budget by 20% and extend its timeline. The sponsor argues that the change is necessary to meet a new regulatory requirement. The portfolio manager must decide how to handle this within the governance framework. What should the portfolio manager do?
Select an answer first
Finished these 2 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PFMP
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PFMP” is a trademark of its owner, used for identification only.