Part of the Portfolio Risk Management domain, which accounts for 15% of the PFMP exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~14–24 in this domain), expect 2–4 from this objective — we provide 28 practice questions to prepare you well beyond it. (estimate)
28questions here
6free pages
7concepts
15%of the exam
Questions 26–28
- 26
What is the primary purpose of prioritizing portfolio risks?
Select an answer first - 27
A portfolio manager has developed a risk response to mitigate a key supplier risk by identifying alternative suppliers. What should the portfolio manager do to implement this response effectively?
Select an answer first - 28
During a quarterly portfolio review, a portfolio manager notices that a previously low-priority risk has increased in likelihood due to market changes. The risk now threatens a strategic objective. What should the portfolio manager do?
Select an answer first
Finished these 3 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PFMP
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PFMP” is a trademark of its owner, used for identification only.