Task 1 Explain When It Is Appropriate to Use a Predictive, Plan-Based Approach. CAPM Practice Questions (Page 5)
Part of the Predictive, Plan-Based Methodologies domain, which accounts for 17% of the CAPM exam. PMI does not publish an official question count, but from its 180-minute exam (~70–120 total, ~12–20 in this domain), expect 4–7 from this objective — we provide 27 practice questions to prepare you well beyond it. (estimate)
27questions here
6free pages
5concepts
17%of the exam
Questions 21–25
- 21
A project is divided into several sequential parts, such as 'Design', 'Build', and 'Test'. Each part produces a unique deliverable and is completed before the next one begins. What are these parts called?
Select an answer first - 22
A project manager is creating the work breakdown structure (WBS) for a predictive project. The project manager needs to decompose the project work into manageable pieces. Which component is the lowest level of the WBS?
Select an answer first - 23
A project manager is planning a predictive project. Which activity is performed during the planning process group?
Select an answer first - 24
In a predictive project, what is the primary purpose of the upfront planning effort?
Select an answer first - 25
A project manager is leading a project with a team that is distributed across multiple time zones and rarely meets in person. Which aspect of a predictive approach is most critical to manage in this virtual environment?
Select an answer first