Part of the Predictive, Plan-Based Methodologies domain, which accounts for 17% of the CAPM exam. PMI does not publish an official question count, but from its 180-minute exam (~70–120 total, ~12–20 in this domain), expect 4–7 from this objective — we provide 9 practice questions to prepare you well beyond it. (estimate)
9questions here
2free pages
3concepts
17%of the exam
Questions 6–9
- 6
Which artifact in a predictive, plan-based project is composed of the approved WBS, the WBS dictionary, and the project scope statement?
Select an answer first - 7
A project manager calculates a cost variance (CV) of +$5,000. Which interpretation is correct?
Select an answer first - 8
A project manager is documenting project controls for a predictive project. The sponsor wants to use earned value management to monitor performance. The project manager has the scope baseline and cost baseline approved. What is missing to establish the performance measurement baseline (PMB)?
Select an answer first - 9
A project manager is establishing the performance measurement baseline (PMB) for a new product development project. The sponsor wants to track cost and schedule performance using earned value management. The project manager has the scope baseline and schedule baseline approved. What must be done to complete the PMB?
Select an answer first
Finished these 4 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to CAPM
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “CAPM” is a trademark of its owner, used for identification only.