Part of the Understand key concepts relating to projects and PRINCE2 domain, which accounts for 3% of the PRINCE2-FOUNDATION-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~1–1 in this domain), expect 1–1 from this objective — we provide 15 practice questions to prepare you well beyond it. (estimate)
15questions here
3free pages
5concepts
3%of the exam
Questions 11–15
- 11
A company is considering whether to treat a new initiative as a project. The initiative involves developing a new product, and the company expects to deliver it in six months. After delivery, the product will be maintained by the operations team. Which characteristic is essential for this initiative to be considered a project?
Select an answer first - 12
A project to upgrade a hospital's patient records system is in progress. The project manager is reviewing the project's performance and needs to report on the six aspects of performance. Which of the following is NOT one of the six aspects of project performance?
Select an answer first - 13
A project manager is new to PRINCE2 and is trying to understand how the integrated elements work together. The project manager reads that the project must be 'justified by business reasons' and that the project must 'learn from experience.' These are examples of which integrated element?
Select an answer first - 14
A project manager is responsible for a project to implement a new payroll system. The project manager has created a work breakdown structure, assigned tasks to the team, and is now tracking progress against the plan. The project manager also holds weekly team meetings to address concerns and keep the team motivated. Which aspect of project management is the project manager demonstrating by holding these meetings?
Select an answer first - 15
A project manager is reviewing the project's budget, schedule, and product specifications. Which two of the six aspects of project performance are they primarily checking?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.