MSP Foundation (5th edition)

Domain 2Objective 1

Assess the Component Parts of the Programme Strategy, Programme Plans, and the Plan-Do-Check-Act (PDCA) Cycle MSP-FOUNDATION-5TH-EDITION Practice Questions (Page 4)

Part of the Understand how to apply and tailor relevant aspects of the MSP themes in context domain, which makes up ~40% of our current practice bank. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~10–16 in this domain), expect 1–2 from this objective — we provide 26 practice questions to prepare you well beyond it. (estimate)

26questions here
6free pages
3concepts

Questions 16–20

  1. 16expert · hard

    A software company is running a programme to develop a new product. The programme plan and project plans are in place. During a 'Check' phase review, the programme manager finds that one project is consistently missing its milestones, which is causing delays in other projects. The project manager blames a lack of resources. The programme manager suspects the project plan is unrealistic. What should the programme manager do first?

    Select an answer first
  2. 17expert · hard

    An energy company is starting a programme to transition to renewable sources. The programme strategy includes a vision, a benefits profile, and a risk register. The board is concerned that the benefits profile is not aligned with the vision. The vision is 'to be the leading renewable energy provider in the region'. The benefits profile includes 'reduce operational costs by 10%'. What is the most significant issue with this benefits profile?

    Select an answer first
  3. 18expert · hard

    A non-profit organisation is running a programme to improve its fundraising. The programme team has been using the PDCA cycle. In the 'Check' phase, they find that the new donation process has increased donations by 5%, but the target was 15%. The team is unsure why the target was not met. What is the most appropriate next step?

    Select an answer first
  4. 19expert · hard

    A public sector organisation is running a programme to improve citizen services. The programme has completed two full PDCA cycles on a pilot process. The 'Check' phase of the second cycle shows that the process is now stable and meeting all targets. However, the programme sponsor wants to continue making improvements to the process. What is the most appropriate action for the programme team?

    Select an answer first
  5. 20application · medium

    An IT services company is using the PDCA cycle to improve its incident response process. In the 'Act' phase, the team has successfully reduced the average response time by 30% over two cycles. What is the most appropriate action for the team to take in the 'Act' phase now?

    Select an answer first