Questions 11–15
- 11
During system testing, a major defect is found that requires a significant redesign. Fixing it will extend the schedule by three weeks and increase costs by 15%. The product owner states that time-to-market is the top priority, while the quality manager insists the defect must be fixed before release. The project sponsor is willing to accept some risk. What should the test manager recommend?
Select an answer first - 12
A test project is facing a critical decision: a new regulatory requirement mandates additional security testing that will add 20% more work. The project has a fixed budget and a fixed release date. The test manager must recommend a course of action. Which approach best addresses the trade-offs?
Select an answer first - 13
Which tracking technique is specifically designed to show the amount of work remaining over time, commonly used in agile projects?
Select an answer first - 14
Which technique is used to develop realistic schedules by estimating durations and identifying dependencies?
Select an answer first - 15
A change request proposes adding a new test tool that requires integration with the existing test management system. The change control board (CCB) asks the test manager to assess the impact. Which factor is most important to include in the impact assessment?
Select an answer first