Examers.io
ExamsOrganizationsHow it worksPricingHelp & FAQ
ISTQB logo

Certified Tester Expert Level Test Management Operational Test Management

Domain 2Objective 2

Execution and Monitoring CTEL-TM-OTM Practice Questions (Page 2)

Part of the Project Management Essentials domain, which makes up ~20% of our current practice bank.

31questions here
7free pages
8concepts

Questions 6–10

  1. 6application · medium

    A test manager is preparing the weekly status report for a system integration testing phase. The burn-down chart shows that the team has completed 60% of planned test cases, but the remaining test cases are more complex than originally estimated. The schedule has a 10% buffer. What is the most appropriate way to communicate this in the status report?

    Select an answer first
  2. 7application · medium

    A test manager receives a change request to replace the test data management tool mid-project. The request is urgent because the current tool has a licensing issue. What is the correct first step in the change control process?

    Select an answer first
  3. 8application · medium

    During the execution of a test phase, the test manager notices that the team has spent 80% of the planned time but completed only 60% of the test cases. The burn-down chart confirms the trend. What is the most appropriate corrective action?

    Select an answer first
  4. 9foundation · easy

    Which of the following is a key component of a change control process?

    Select an answer first
  5. 10foundation · easy

    When scope, time, and cost constraints conflict, what should guide the prioritization of these constraints?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by ISTQB. “CTEL-TM-OTM” is a trademark of its owner, used for identification only.