Part of the Securing the ICS Network domain, which makes up ~16% of our current practice bank. EC-Council does not publish an official question count, but from its 120-minute exam (~50–80 total, ~8–13 in this domain), expect 1–2 from this objective — we provide 45 practice questions to prepare you well beyond it. (estimate)
45questions here
9free pages
7concepts
Questions 36–40
- 36
A natural gas pipeline company has a legacy SCADA server that is vulnerable to a known buffer overflow exploit. The vendor has not released a patch and will not support the server after next year. The security team wants to protect the server until it is replaced. Which virtual patching approach is most appropriate?
Select an answer first - 37
What is a primary security risk associated with legacy machines in ICS networks?
Select an answer first - 38
A transportation authority operates a legacy signaling system that is critical for safety. The system is end-of-life and cannot be patched. The authority has a limited budget and must maintain operations for at least five more years. They are considering three options: (1) replace the entire system now, (2) implement compensating controls and replace in five years, or (3) do nothing and hope for the best. Which option best balances risk and operational constraints?
Select an answer first - 39
A power generation plant has a legacy turbine control system running Windows 2000. The system is on a flat network with the plant's business LAN. The plant manager wants to reduce risk but has a very limited budget. The security team proposes two options: (1) deploy a network IPS with virtual patching for Windows 2000 vulnerabilities, or (2) create a VLAN for the legacy system and configure a firewall to allow only the necessary HMI traffic. The VLAN creation requires a network engineer for 2 days, while the IPS deployment requires purchasing a new appliance. Which option is the BEST use of the limited budget?
Select an answer first - 40
A chemical plant has a legacy control system running Windows XP that is connected to a business network with internet access. The plant has a limited budget and must choose between two projects: (1) deploying a network IPS with virtual patching for Windows XP vulnerabilities, or (2) creating a VLAN for the legacy system with a firewall. The VLAN creation requires a network engineer for 3 days, while the IPS requires purchasing a new appliance. The plant manager wants to reduce risk as quickly as possible. Which project should the plant choose?
Select an answer first