Part of the Organizational Development and Alignment domain, which accounts for 16% of the PMI-PMOCP exam. PMI does not publish an official question count, but from its 165-minute exam (~65–110 total, ~10–18 in this domain), expect 3–5 from this objective — we provide 41 practice questions to prepare you well beyond it. (estimate)
41questions here
9free pages
11concepts
16%of the exam
Questions 36–40
- 36
A benchmarking study revealed that the organization's project closure process is significantly slower than industry best practice. The PMO has identified that the root cause is a manual approval workflow. What should the PMO do to drive continuous improvement?
Select an answer first - 37
A maturity assessment revealed that project managers lack skills in stakeholder engagement, but the organization has a very limited training budget. The PMO must decide how to address the gap. The organization has a small group of highly experienced project managers who excel at stakeholder engagement. What is the most cost-effective approach that still addresses the gap?
Select an answer first - 38
When selecting KPIs for OPM maturity, what should be the primary basis for choosing them?
Select an answer first - 39
Which method is commonly used to evaluate the effectiveness of a training program after it has been delivered?
Select an answer first - 40
What is a key consideration when designing a training program to address OPM maturity gaps?
Select an answer first