Part of the Manage AI Model Development and Evaluation domain, which accounts for 16% of the PMI-CPMAI exam. PMI does not publish an official question count, but from its 160-minute exam (~65–105 total, ~10–17 in this domain), expect 2–3 from this objective — we provide 21 practice questions to prepare you well beyond it. (estimate)
21questions here
5free pages
7concepts
16%of the exam
Questions 1–5
- 1
If a model meets all success criteria but the infrastructure review reveals insufficient compute capacity for expected traffic, what should the go/no-go decision be?
Select an answer first - 2
What is the main goal of robustness assessment in the context of model operationalization?
Select an answer first - 3
A churn-prediction model was trained on customer data from 2020-2023. The team evaluates it on a holdout set from 2023 and achieves strong performance. Before the go/no-go decision, the data science lead suggests evaluating the model on a dataset from the first quarter of 2024, which was not used in training. What is the primary purpose of this additional evaluation?
Select an answer first - 4
What is the purpose of reviewing operational procedures during the go/no-go assessment?
Select an answer first - 5
A team is reviewing a demand-forecasting model for operationalization. The model meets all performance targets. However, the operational procedures document does not include a rollback plan, and the monitoring dashboard is not yet configured to track prediction drift. What should the team do?
Select an answer first