PMIConstruction Professional (PMI-CP)
Domain 3Objective 4
Implement the Advanced Work Packaging Model and Tools Effectively PMI-CP Practice Questions (Page 4)
Part of the Strategy and Scope Management domain, which accounts for 15% of the PMI-CP exam.
35questions here
7free pages
8concepts
15%of the exam
Questions 16–20
- 16
During the development of construction work packages, the team notices that several packages contain incomplete engineering information, requiring field crews to wait for clarifications. Which Lean principle is most directly violated?
Select an answer first - 17
Which statement best describes the Advanced Work Packaging (AWP) model?
Select an answer first - 18
In the Last Planner System, what is a 'should-can-will-did' planning process?
Select an answer first - 19
A project team is using the Last Planner System to improve workflow reliability. During a weekly work planning meeting, a trade contractor commits to completing a task that requires a permit that has not yet been obtained. What is the most appropriate action?
Select an answer first - 20
A project team is implementing AWP and has completed the 'Path of Construction' and the 'Construction Work Package' (CWP) definition. According to the AWP stages and process steps, what is the next major deliverable the team should produce?
Select an answer first