
PMIConstruction Professional (PMI-CP)
Domain 3Objective 2
Implement and Manage the Change Order Process Effectively and Deliver Project Benefits and Value PMI-CP Practice Questions (Page 5)
Part of the Strategy and Scope Management domain, which accounts for 15% of the PMI-CP exam.
25questions here
5free pages
5concepts
15%of the exam
Questions 21–25
- 21
What is a potential downfall of using technology for change order management?
Select an answer first - 22
A project manager is evaluating two change management tools. Tool A has advanced automation and integrates with the project schedule, but has a steep learning curve. Tool B is simple and easy to use but lacks automation and requires manual updates. The team is small and changes are infrequent. Which tool should the project manager choose?
Select an answer first - 23
A project manager is leading a project that is in the execution phase. The change control process was finalized during planning. A major change request is submitted that would alter the project's scope and require re-baselining. The project sponsor is concerned about the impact on benefits. What should the project manager do?
Select an answer first - 24
What is a potential benefit of using technology to manage scope changes?
Select an answer first - 25
A project manager is designing a change process for a hybrid project that uses both waterfall and agile components. The process must be flexible enough for agile parts but controlled enough for waterfall parts. Which approach is most effective?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PMI-CP
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-CP” is a trademark of its owner, used for identification only.