Task 5 Identify Sustainability-Related Activities in Each Project Management Phase CSPP Practice Questions (Page 3)
Part of the Project Management Considerations domain, which accounts for N/A / 23% of the CSPP exam.
29questions here
6free pages
5concepts
N/A / 23%of the exam
Questions 11–15
- 11
A project to decommission an old data center is nearing completion. The project manager wants to ensure that sustainability is considered in the closure phase. Which activity should the project manager perform?
Select an answer first - 12
A project is in the monitoring and control phase. The sustainability metrics show that the project is on track, but a stakeholder raises concerns about the environmental impact of a specific process. The project manager needs to address the concern without derailing the project. What is the best action?
Select an answer first - 13
A construction project is complete, and the project manager is preparing for closure. The project included a requirement for responsible disposal of construction waste. Which closure-phase activity ensures this requirement is met?
Select an answer first - 14
In the monitoring and control phase, which activity helps ensure sustainability performance stays aligned with objectives?
Select an answer first - 15
A construction company is initiating a new office building project. The project sponsor wants to ensure that sustainability is considered from the very beginning. The project manager is asked to identify the first set of sustainability-related activities. Which activity should the project manager perform during the initiating phase?
Select an answer first