Be Able to Identify, Analyse and Distinguish Between Appropriate and Inappropriate Application of Portfolio Delivery Practices and Techniques to a Scenario MOP-PRACTITIONER Practice Questions (Page 3)

Part of the Portfolio delivery cycle domain, which makes up ~27% of our current practice bank.

26questions here
6free pages
6concepts

Questions 11–15

  1. 11application · medium

    A portfolio of IT projects shares a single pool of specialist developers. Each project manager has been told to secure the developers they need for their project. The portfolio office notices that projects are being delayed because developers are being pulled between projects. What is the most appropriate portfolio-level resource management approach?

    Select an answer first
  2. 12expert · hard

    A portfolio has a risk that a key supplier may go out of business, affecting three projects. The risk has been identified in each project's risk register, but each project is planning a different mitigation approach. The portfolio risk manager is concerned about the inconsistency. What is the most appropriate portfolio-level risk management action?

    Select an answer first
  3. 13application · medium

    A portfolio risk manager maintains a risk register that lists risks for each individual project. At the monthly portfolio board meeting, the board reviews the top risk from each project. The board is concerned that this approach does not give a complete picture of portfolio-level risk. What is the most appropriate improvement?

    Select an answer first
  4. 14expert · hard

    A portfolio board is reviewing a high-risk, high-value initiative. The board is receiving detailed progress reports from the project manager, but the board is concerned that the reports are too optimistic and do not highlight risks. The board is considering asking the project manager to provide a more balanced view. What is the most appropriate management control practice to address this concern?

    Select an answer first
  5. 15foundation · easy

    A portfolio manager allocates resources to initiatives based on the initiative manager who asks first. Why is this an inappropriate resource management practice?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.