Know Facts, Terms and Concepts Relating to Implementing, Sustaining and Measuring Portfolio Management MOP-FOUNDATION Practice Questions (Page 3)
Part of the Implement, sustain and measure domain, which makes up ~19% of our current practice bank. PeopleCert does not publish an official question count, but from its 40-minute exam (~15–25 total, ~3–5 in this domain), expect 1–1 from this objective — we provide 16 practice questions to prepare you well beyond it. (estimate)
16questions here
4free pages
2concepts
Questions 11–15
- 11
A telecommunications company has implemented portfolio management. The portfolio office wants to demonstrate to stakeholders that the function has improved the organization's ability to prioritize projects. Which measure would best demonstrate this?
Select an answer first - 12
A global consumer goods company is implementing portfolio management. The organization has a strong culture of innovation and dislikes rigid processes. The implementation lead must choose an approach that respects this culture while still delivering the benefits of portfolio management. The lead is considering a big bang approach to get it over with quickly, versus an incremental approach. Which factor is most important in this decision?
Select an answer first - 13
A public-sector organization has a mature project delivery culture but no portfolio management. The portfolio office lead has been given 12 months to embed portfolio management and must show tangible benefits early to secure continued funding. The organization's governance boards are risk-averse and prefer incremental change. Which approach should the lead recommend?
Select an answer first - 14
A pharmaceutical company has implemented portfolio management. The R&D director claims the new process has slowed down decision-making. The portfolio office has data showing that the average time to approve new projects has increased from 4 weeks to 6 weeks, but the percentage of projects that fail to meet strategic objectives has decreased from 30% to 10%. How should the portfolio office respond to the R&D director's claim?
Select an answer first - 15
A technology company has implemented portfolio management. The CEO wants to know if the new approach has actually improved decision-making. The portfolio office has data on the number of projects initiated, the average time to approve new projects, and the percentage of projects that meet strategic objectives. Which combination of measures would best assess the impact of portfolio management on decision-making?
Select an answer first