Part of the Implement, sustain and measure domain, which makes up ~19% of our current practice bank. PeopleCert does not publish an official question count, but from its 40-minute exam (~15–25 total, ~3–5 in this domain), expect 1–1 from this objective — we provide 24 practice questions to prepare you well beyond it. (estimate)

24questions here
5free pages
8concepts

Questions 6–10

  1. 6expert · hard

    A large organization has been running portfolio management for two years. The portfolio office is under pressure to show value. They decide to implement a new tool that automates reporting, but they roll it out without training, and they remove the existing monthly review meetings to save time. They measure success by the number of automated reports generated. Which combination of implementation, sustaining, and measuring approaches is being applied?

    Select an answer first
  2. 7application · medium

    An organization is implementing portfolio management and wants to measure its success. They plan to use a phased implementation, starting with a pilot in one business unit, and to measure success by tracking the percentage of projects that meet their stated benefits. Which combination of implementation and measurement approaches is appropriate?

    Select an answer first
  3. 8foundation · easy

    An organization implements portfolio management by engaging stakeholders, piloting the approach, and then rolling it out. To sustain it, they hold regular reviews and adapt processes based on feedback. To measure it, they track benefits realization against predictions. Which statement best describes this overall application?

    Select an answer first
  4. 9foundation · easy

    An organization implements portfolio management by copying a framework from another company without adaptation. To sustain it, they stop all reviews after the first year. To measure it, they count the number of portfolio documents produced. Which statement best describes this overall application?

    Select an answer first
  5. 10foundation · easy

    A public sector organization is introducing portfolio management for the first time. The portfolio office starts by running awareness sessions for senior stakeholders, then pilots the approach on a small set of projects before rolling it out more widely. Which statement best describes this implementation approach?

    Select an answer first