Questions 6–10
- 6
An operational test manager is working on a project that is part of a larger program. The program has a risk management process that requires all risks to be categorized and reported monthly. The test manager has identified a risk that is specific to the test phase and does not affect other program components. The test manager is unsure whether to include it in the program-level risk report. What should the test manager do?
Select an answer first - 7
An operational test manager is explaining the purpose of risk management to a new team member. The team member asks, 'Why do we spend time on risk management when we could be testing?' Which response best reflects the purpose of risk management in operational test management?
Select an answer first - 8
An operational test team is planning the testing of a new regulatory reporting system. The test manager wants to ensure that all relevant risks are identified. Which approach best aligns with stakeholder engagement in risk management?
Select an answer first - 9
During an operational test project, a risk was identified that a key test environment might be unavailable due to scheduled maintenance by the infrastructure team. The risk was assessed as medium priority, and a contingency plan was developed to use a cloud-based environment. Two weeks before the test execution, the infrastructure team announces that the maintenance will occur during the test window. The risk trigger was defined as 'maintenance scheduled during test window'. What should the test manager do?
Select an answer first - 10
An operational test manager is new to a project and is reviewing the risk register. The register contains a risk described as 'The test environment may be slow, causing delays.' The test manager notices that the likelihood and impact are not assessed. What is the first step the test manager should take to improve the risk management process?
Select an answer first