Questions 16–20
- 16
A test manager is evaluating exit criteria for a project. The criteria include a defect detection percentage (DDP) of at least 90%, and the current DDP is 85%. The project manager argues that the DDP is not important because the system is not high-risk. What should the test manager do?
Select an answer first - 17
Which of the following is an essential element of a test report?
Select an answer first - 18
Which stakeholder would most likely need a high-level summary of test results rather than detailed defect reports?
Select an answer first - 19
A test manager is writing a test report for a project that is nearing completion. The report must be concise but informative for stakeholders. Which approach is best?
Select an answer first - 20
A test manager must communicate test results to a project sponsor who is focused on cost and schedule. The sponsor is not interested in technical details. The test results show that the exit criteria are not met, but the sponsor wants to release to avoid cost overruns. What should the test manager do?
Select an answer first