Questions 11–15
- 11
What is the purpose of reporting deviations in exit criteria status?
Select an answer first - 12
A test manager is evaluating exit criteria for a release. The criteria include 100% of high-risk test cases passed and zero open severity-1 defects. The current status shows 98% of high-risk tests passed and one open severity-1 defect that is being fixed. The release date is in two days. What should the test manager do?
Select an answer first - 13
A test manager is evaluating exit criteria for a release. The criteria include 95% test case pass rate, zero open critical defects, and 100% coverage of high-risk requirements. The current metrics show a 93% pass rate, one open critical defect, and 98% high-risk coverage. The project sponsor wants to release on schedule. What should the test manager do?
Select an answer first - 14
How does exit criteria evaluation support release decisions?
Select an answer first - 15
A test manager must report exit criteria status to two audiences: the executive steering committee and the development team. The exit criteria include defect density, test coverage, and schedule adherence. What is the most appropriate reporting approach?
Select an answer first